How to Choose a Commercial Solar EPC in Ireland 2026: Due Diligence Guide
Picking the wrong EPC is the single biggest risk in commercial solar. Here is a structured 2026 Irish due-diligence process to find the right contractor, write a strong contract, and avoid the common mistakes.
By Smart Solar Editorial · Updated 15 May 2026 · 10 min read

Selecting the right Engineering, Procurement and Construction (EPC) contractor is the single most consequential decision in a commercial solar project. The right EPC delivers a system that performs to spec for 25+ years with minimal intervention; the wrong EPC delivers chronic underperformance, warranty disputes, and grant drawdown delays that can cost more than the original install. This guide outlines the 2026 Irish due-diligence process, the tender structure, contract considerations, and the warning signs to watch for.
What an EPC actually does
A commercial solar EPC takes single-point responsibility for designing, procuring and installing the system, plus typically commissioning and a defined warranty period. The scope normally includes:
- Concept and detailed design (electrical, structural, planning support)
- Equipment procurement (modules, inverters, mounting, cabling, switchgear)
- Installation (mechanical and electrical)
- ESB Networks NC7 application and liaison
- SEAI Non-Domestic Microgen Grant application
- Commissioning and handover
- Defects warranty (typically 1-2 years on workmanship)
- Optional O&M agreement (separate contract, typically 5-25 years)
The EPC carries design, procurement, programme and quality risk during construction. After handover, the system owner carries operational risk, mitigated by the O&M agreement.
The tender shortlist
For a typical Irish commercial solar project (100-500 kWp), aim for a tender shortlist of 3-5 EPCs. Sources:
- SEAI Registered Contractors list. Mandatory for NDMG grant projects.
- Industry references. Other Irish businesses in your sector who have installed solar.
- Sector specialists. Some EPCs specialise in dairy farms, manufacturing, hotels, or institutional clients.
- Geographic coverage. Some EPCs are strong in specific regions (Cork, Galway, Dublin commuter belt).
Major Irish EPCs active in 2026 include Activ8 Solar Energies, Enerpower, Powerlink, Mercury Engineering, John Sisk, ESB Smart Energy Services, Solar Electric Ireland, NRG Solar, and a growing number of regional contractors. For specialised sectors (Seveso, data centres, listed buildings) the shortlist narrows significantly.
The tender package
A good tender package gives every EPC the same information so quotes are comparable. Include:
- Site information. Location, building details, single-line electrical drawing, recent MV90 import profile (12 months), roof plan and structural drawings if available.
- Scope statement. Project objectives (kWp target, export limit policy, target self-consumption, integration with battery/EV charging).
- Technical requirements. Preferred inverter brands or open spec, module quality tier, mounting type, monitoring requirements, NC7 strategy.
- Commercial requirements. Pricing format (lump sum, schedule of rates), grant assignment policy, warranty terms, O&M offer.
- Programme. Target dates for site survey, NC7 submission, grant submission, installation, commissioning.
- Evaluation criteria. Weighting between price, technical, programme, references, warranty (typically 40-60% price, 20-30% technical, 10-20% references and team).
Provide the same package to each EPC and require structured responses against the criteria.
Technical due diligence
For each shortlisted EPC, verify:
Track record
- At least 10-20 commercial projects completed in Ireland
- At least 3 projects at your size and sector
- Project list with kWp, completion date, technology, client (with consent for reference checks)
- References you can actually call (not just paper)
- Visit at least one completed installation
Team
- Named project manager with directly relevant experience
- In-house design engineers (avoid EPCs that fully sub-contract design)
- In-house installation teams (or long-term sub-contractor relationships)
- ESB Networks NC7 specialist (NC7 is a critical path item)
- Commissioning engineer with electrical qualifications
Financial standing
- 3 years' filed accounts (CRO available)
- Adequate turnover for your project size (typical rule: project should be no more than 20% of annual turnover)
- No major legal disputes or director changes
- Adequate professional indemnity (€2M+) and public liability (€6.5M+) insurance
Technical capability
- SEAI registration covering your kWp range
- Safe Pass and Safe Work at Heights certification across team
- Recent inverter manufacturer training (SolarEdge, Huawei, SMA - whichever you specify)
- ECSSA or comparable electrical qualifications
- HSA-compliant safety management system
Contract structure
A solid commercial solar EPC contract includes:
Scope and specification
- Detailed bill of materials with brands and models specified
- Performance specification (expected kWp, expected annual generation)
- Acceptance criteria (commissioning test results, performance ratio threshold)
- Change control procedure
Programme
- Defined milestones (design freeze, NC7 submission, equipment delivery, install start, install complete, commissioning, handover)
- Liquidated damages for late delivery (typically 0.1-0.25% of contract value per week, capped)
- Force majeure provisions
Payment
- Stage payments aligned to milestones (typical: 10% on order, 30% on equipment delivery, 40% on install complete, 15% on commissioning, 5% on grant drawdown)
- Retention (typically 5%) released 6-12 months after handover
- Grant assignment terms (if applicable)
Warranty and defects
- Workmanship warranty (typically 1-2 years minimum, ideally 5)
- Performance warranty (expected kWh, with measurement methodology)
- Pass-through of equipment warranties (modules, inverters)
- Defects liability period and response times
- Optional extended warranty terms
Performance guarantees
- Expected first-year kWh output with measurement window
- Performance ratio threshold (typically 80%+ on commercial)
- Compensation mechanism for underperformance
- Exclusions (irradiance shortfall, grid outages, force majeure)
Insurance and indemnity
- Public liability minimum €6.5M
- Employers liability minimum €13M
- Professional indemnity minimum €2M
- Contractor all-risks insurance during construction
- Indemnity for IP infringement on monitoring/software
Termination
- Defined grounds for termination
- Step-in rights for the owner
- Handover of documentation, design files and software access in event of termination
Red flags to walk away from
- Refusal to provide three reference sites you can visit
- Quote that is significantly lower than peers (often indicates corners being cut or specification gaps)
- Vague specification (just "modules, inverters, mounting" without brands and models)
- Refusal to commit to performance guarantees
- Demand for >50% payment upfront
- No in-house design capability
- Director or company name changes in last 18 months
- No SEAI registration when NDMG is part of the project
- Aggressive sales tactics or "limited time discount" pressure
- Unwillingness to negotiate contract terms
The site survey
Before signing, the EPC must do a proper site survey covering:
- Roof structural assessment (often with subcontracted structural engineer)
- Roof condition and remaining service life
- Existing electrical infrastructure (switchgear, transformer, cabling)
- Site access for cranes, MEWPs, deliveries
- Shading study (full year, hour-by-hour)
- Health and safety assessment
- NC7 feasibility review with ESB Networks
A quote based on Google Maps and a phone call is not a real quote. Walk away from EPCs that skip the site survey.
Pricing benchmarks for 2026
To sanity-check quotes, indicative all-in installed prices in Ireland in 2026:
- 50 kWp: €1,200-€1,700/kWp (€60-€85k total)
- 100 kWp: €1,100-€1,500/kWp
- 200 kWp: €900-€1,300/kWp (€180-€260k total)
- 500 kWp: €850-€1,160/kWp (€420-€580k total)
- 1 MWp: €750-€1,100/kWp (€750k-€1.1M total)
These are pre-grant. Wide variation depends on roof type, ground vs roof, complexity, inverter brand, and EPC margin. A quote 25%+ outside this range deserves close scrutiny in either direction.
Bottom line
Choosing the right commercial solar EPC in Ireland in 2026 is a structured process: tender to 3-5 contractors, verify track record and team, write a strong contract with clear performance guarantees, and never sign anything without a proper site survey. The marginal cost of due diligence is small; the cost of getting it wrong can be the entire value of the project. Take your time, ask hard questions, and walk away from anyone who fails the basics.
Get 3 free commercial solar quotes — free and no obligation.
Frequently asked questions
How many EPCs should I tender to for a commercial solar project?
3-5 is the sweet spot. Fewer than three loses competitive pressure; more than five becomes administratively burdensome and dilutes the seriousness with which each EPC responds.
What financial standing should I expect from an EPC?
3 years of filed accounts (available from the CRO), turnover at least 5x your project size, adequate professional indemnity (€2M+) and public liability (€6.5M+) insurance, no major legal disputes or recent director changes.
What payment structure is fair for a commercial solar EPC contract?
Stage payments aligned to milestones - typically 10% on order, 30% on equipment delivery, 40% on install complete, 15% on commissioning, 5% on grant drawdown. Plus retention of 5% released 6-12 months after handover.
What performance guarantee should I require?
Expected first-year kWh output with a defined measurement window, performance ratio threshold of 80%+ on commercial, and a compensation mechanism for underperformance. Exclusions are typically irradiance shortfall, grid outages and force majeure.
What is a red flag when reviewing EPC quotes?
Quote significantly below peers (often indicates corners being cut), vague specification without brands and models, refusal to commit to performance guarantees, demand for >50% upfront payment, no in-house design capability, and no SEAI registration when NDMG grant is part of the project.