EXEED Grant for Commercial Solar: Up to 30% Funding, Capped at €3M
When your solar project is part of a broader energy strategy, EXEED can pay more than NDMG. Here is how the scheme works, who qualifies and when to choose it.
By Smart Solar Editorial · Updated 4 November 2026 · 10 min read

Most Irish business solar projects go through the Non-Domestic Microgen Grant (NDMG), which is simple and — for applications made between 6 October 2026 and 6 July 2027 — pays an effective 45% of eligible cost up to €325,200 (previously capped at €162,600). For larger projects, or where solar PV is part of a broader energy upgrade involving heat recovery, controls, lighting and process improvement, the SEAI EXEED Certified Grant can be more valuable. EXEED pays up to 30% of eligible costs, capped at €3 million per project. This guide explains when to choose EXEED over NDMG and how the application works in 2026.
What EXEED stands for
EXEED is the Excellence in Energy Efficient Design scheme administered by SEAI. It funds the design and implementation of energy-intensive projects that follow a structured, evidence-based design methodology aligned with ISO 50001 principles. Solar PV is an eligible measure within an EXEED-funded project as long as it sits within a wider energy management framework.
How much you can claim
In 2026 the EXEED grant rates are:
- Design phase: Up to 50% of eligible design costs, typically capped at €200,000
- Investment phase: Up to 30% of eligible capex (large enterprises) or 40-50% (SMEs depending on size and project type)
- Total project cap: €3,000,000
For a 700 kWp solar PV project costing €750,000, EXEED at 30% could fund up to €225,000. During the enhanced NDMG window the same PV would receive €235,200 from the NDMG (the band value, below 45% of cost), so for solar alone the NDMG is currently the better-funded route. EXEED's case rests on the wider programme of measures it can fund.
Eligibility
To qualify in 2026 a project must:
- Have a defined energy outcome (typically a kWh, primary energy or CO2 reduction target).
- Follow the SEAI-published EXEED design methodology with project gateways and certified design support.
- Use an SEAI-approved energy auditor or design partner.
- Have not received other state support for the same measures.
- Be implemented within a defined timeline post-letter-of-offer.
NDMG vs EXEED: side by side
| Factor | NDMG | EXEED |
|---|---|---|
| Headline rate | €600 / €400 / €300 per kWp bands, max 45% of cost (enhanced, to 6 Jul 2027) | Up to 30% (LE) / 50% (SE) |
| Cap | €325,200 (enhanced window; €162,600 before) | €3,000,000 |
| Eligible scope | Solar PV only | Wider energy upgrades |
| Approval timeline | 4-8 weeks | 3-6 months |
| Design rigour | Light | Heavy (ISO 50001 aligned) |
| Best for | Standalone PV up to ~400 kWp | Large multi-measure energy programmes |
When to choose EXEED
EXEED becomes more attractive than NDMG when:
- Your PV system is well above 1,000 kWp, where the NDMG stops adding grant.
- The PV is part of a broader project including lighting, controls, heat pumps, compressed air, refrigeration or building envelope upgrades.
- You operate under an existing ISO 50001 energy management system.
- Internal capability exists (or you have a design partner) to handle the higher documentation burden.
- The project is strategically visible enough that the additional rigour delivers internal value beyond grant funding.
Manufacturing plants, food processors, data centres, hospitals, district heating projects and large hotels are the typical EXEED candidates.
When NDMG is the better choice
- Pure solar PV projects up to 1,000 kWp — especially during the enhanced 45% window.
- Time-sensitive projects where the 3-6 month EXEED design phase is unworkable.
- Smaller organisations without the energy management infrastructure to handle EXEED documentation.
- Sites where the broader energy upgrade is already complete.
A worked example: 1 MWp food processor
A Cork food processor consuming 4 GWh/year is planning a 1 MWp rooftop solar project plus a parallel heat-recovery upgrade and lighting refit.
Option A: NDMG (PV only)
- Capex: €920,000
- Grant: €325,200 (enhanced NDMG maximum)
- Net capex: €594,800
Option B: EXEED (full programme: PV + heat recovery + lighting)
- Capex: €1,800,000
- Grant: 30% = €540,000
- Net capex: €1,260,000
If only the solar element were funded under EXEED at 30%, the grant on the PV alone would be €276,000 — €49,200 less than the €325,200 the enhanced NDMG pays during its window. EXEED's advantage in this example is the additional ~€264,000 it funds on heat recovery and lighting. The same equipment can never be funded by both schemes, and the NDMG cannot be combined with other State aid on the same installation, so ask SEAI how the two interact for your specific project before you commit.
The trade-off is timeline. EXEED's design phase adds 3-6 months and approximately €40,000-€100,000 of design fees, of which roughly half are themselves grant-funded.
Application process
- Pre-engagement. Discuss the project concept with SEAI's EXEED team before committing capex.
- Design grant application. Submit a defined scope and energy outcome.
- Letter of offer (design). Begin SEAI-aligned design process with an approved partner.
- Investment grant application. After design gateway, submit final scope, capex, expected energy savings.
- Letter of offer (investment). Project commencement window typically 12 months.
- Implementation. With SEAI gate reviews at key milestones.
- Measurement and verification. Demonstrate actual savings versus baseline.
- Drawdown. Phased against milestones.
Total elapsed time from concept to investment drawdown: 9-18 months.
Working with design partners
A short list of design partners with EXEED experience operating in Ireland includes the engineering arms of Mercury Engineering and ESB Smart Energy Services, alongside dedicated energy consultancies. For EPCs, Activ8 Solar Energies, Enerpower, Powerlink and Solar Electric Ireland have all delivered solar within EXEED programmes.
Documentation burden
EXEED requires significantly more documentation than NDMG:
- Energy baseline study (12 months of metered data)
- Investment grade audit
- Designed energy outcome calculation
- Measurement and verification (M&V) plan
- Gate review submissions
- Final M&V report
Budget 4-8 weeks of internal energy-team time across the project life.
Common pitfalls in EXEED applications
Three errors regularly derail otherwise-strong EXEED submissions:
- Starting construction before the letter of offer. SEAI's incentive effect rule means any committed capex (purchase orders, deposits) before EXEED grant approval disqualifies that scope. Even a €5k deposit on inverters can void the entire solar element. Sequence the project so design and tender precede capex by a full quarter.
- Inadequate baseline data. EXEED requires a documented 12-month energy baseline at the granularity needed to evidence savings. Half-hourly electrical interval data is mandatory; thermal sub-metering is increasingly expected. Sites without sub-meters typically spend €8k–€18k retrofitting them before the baseline year can even begin.
- Underspecified Measurement and Verification (M&V) plan. IPMVP Option B (retrofit isolation with all parameter measurement) is the gold standard for solar, but adds €4k–€12k per year in metering and verification engineer fees. Option A (key parameter measurement) is cheaper but exposes you to dispute at final M&V review. Pick the right option at design phase, not at drawdown.
For pure solar PV projects up to 1,000 kWp, NDMG is almost always the right answer — and during the enhanced window to 6 July 2027 it is the better-funded one too. For larger, multi-measure energy programmes - particularly in manufacturing, food, pharma and data centres - EXEED unlocks substantially more grant value but demands the discipline of a structured energy management project. If your CFO wants the maximum grant rate and your COO wants to deliver next month, choose NDMG. If your sustainability director is leading an ISO 50001 programme, EXEED is the right home.
Get 3 free commercial solar quotes — free and no obligation.
Frequently asked questions
How much can EXEED fund for a commercial solar project?
Up to 30% of eligible capex for large enterprises (or 40-50% for SMEs depending on category), capped at €3 million per project. Design phase support is also available at up to 50% of design costs.
Can I stack EXEED with the Non-Domestic Microgen Grant?
Not on the same equipment. You can use EXEED for the overall programme and NDMG separately only if a different specific measure is being funded by each, with no double-counting.
How long does an EXEED application take?
Allow 3-6 months for the design phase, then 4-8 weeks for the investment letter of offer, followed by the implementation window. End-to-end from concept to drawdown is typically 9-18 months.
Do I need ISO 50001 to apply for EXEED?
No, but the design methodology aligns with ISO 50001 principles. Organisations with an existing ISO 50001 management system find EXEED much easier to navigate and document.
Sources & further reading
- EXEED Certified Grant — SEAI
- Non-Domestic Microgeneration Grant — SEAI
- ISO 50001 Energy Management — SEAI